SOP for Project Initiation & Project Creation

Purpose: This Standard Operating Procedure (SOP) outlines the process for initiating and creating implementation projects. This ensures clear communication, efficient resource allocation, and accurate tracking of project execution.

Problem Addressed: Previously, few implementation project tasks and time logging were done within Support projects. This resulted in:

  • Difficulty identifying hours invested by the technical team in implementation projects.
  • Inability for the CPO Team to have a clear view of ongoing implementation efforts.

Benefits of Streamlined Process:

  • Improved transparency and accountability for project execution.
  • Enhanced ability for CPO to track resource allocation for implementation projects.
  • Increased efficiency in project management.
  1. Project Initiation (T+1)

Project initiation will be the initial phase of a project where the project will be defined, planned, and prepared for execution after project win.

Sales team member will submit Project Creation Form for review. Once submitted a ticket with ticket id will be created for the same in Jira for Implementation Team to review.

  • The form will contain request types such as:

Capture.PNG

a) Resource Requirement for Pre-Sales

b) Client specific Development

c) Change Request

d) Implementation

e) Client Onboarding

  • The form should clearly outlineoutline:

    • Client name,name Description,
    • customer
    • Description
    • ERP,
    • Customer ERP
    • PO date, product for which the PO is received, PO amount,
    • tentative
    • Tentative dates for meeting of Implementation team with Client,
    • confirmation
    • Confirmation mail or share point link.

    Sales Team Responsibility:

    • Within 1 business day of securing a new project, Sales team member will submit Project Creation Form to Implementation and CPO Team. 

    CPO Responsibility:

    • Acknowledge receipt of the Project Initiation Form within 1 business day of submission.

     

    2. Project Planning and Resource Allocation (T+4)

    Once thorough review is conducted by Implementation Team, they will create a ticket to CPO team for project creation.

    This ticket/form will include details such asas:

    • Project Title,Title & Primary focus of the project,project
    • SPOC,
    • SPOC
    • Resources
    • Project needed,Deliverables & Project Deliverables,Plan
    • Project Plan,Timeline
    • Project Timeline,
    • Project Initiation Ticket.

    Kickoff Meeting:

    • CPO will lead a kickoff meeting with the implementation team to discuss the project details based on the form submitted.
    • This meeting should occur within 2 business days of receiving the Project Initiation Form.

    Project Plan:

    • The implementation team will collaborate to develop a detailed project plan within 3 business days of the kickoff meeting. This plan should outline:
      • Project scope and deliverables
      • Key milestones and deadlines
      • Required resources and tasks
      • Communication protocols

    Project Creation:

    • Within 1 business day of the kickoff meeting, CPO will create a dedicated JIRA project for the new initiative.

    Implementation Responsibility:

    • Collaboration and Development of Project Plan within 3 business days of kickoff meeting.

    CPO Responsibility:

    Conduct Kickoff meeting and project creation based on inputs received.

    3. Project Execution and Monitoring (Ongoing)

    Resource Allocation:

    • Upon receiving the project plan, CPO will finalize resource allocation within 2 business days. This includes assigning team members and ensuring all necessary personnel are available to support the project.

    Project Execution:

    • The implementation team will commence project execution following the approved project plan.
    • Team members will be responsible for completing their assigned tasks and adhering to the established timeline.
    • Once initial tasks have been created, new tasks willcan only be added only on approval basis.

    Regular Monitoring:

    • CPO and the project manager will conduct weekly project reviews to assess progress, identify any potential roadblocks, and ensure the project stays on track based on Jira Data
    • CRM Manager (Manisha) will conduct weekly review of finances. Track project expenditures against the approved budget to ensure financial compliance.

    RACI (Responsibility, Accountability, Consulted, Informed)

    Task/Activity Responsible Accountable Consulted Informed
    Project Initiation Form Submission Sales Team CPO -
    Implementation Team
    Kickoff Meeting Scheduling CPO CPO -
    Implementation Team
    Project Creation CPO CPO -
    Implementation Team
    Project Plan Development Implementation Team Implementation Team CPO -
    Resource Allocation CPO CPO Implementation Team -
    Project Execution Implementation Team Implementation Team CPO, Project Manager -
    Regular Project Reviews CPO, Project Manager/ CRM Manager CPO, Project Manager/ CRM Manager Implementation Team -
    Finance ReviewCRM ManagerCRM ManagerCPO-